Workkeys Math Practice Test 2025 – The All-in-One Guide to Mastering Math Skills for Exam Success!

Question: 1 / 400

How many person-hours are needed to clear a driveway and pour concrete, if breaking up the driveway takes 14 hours and pouring concrete takes 8 hours?

20 person-hours

22 person-hours

To determine the total person-hours needed to clear a driveway and pour concrete, you simply add together the time required for each task. In this scenario, breaking up the driveway requires 14 hours, and pouring concrete takes an additional 8 hours.

Calculating the total, you would perform the following addition:

14 hours (breaking up the driveway) + 8 hours (pouring concrete) = 22 hours total.

Therefore, the total person-hours needed for both activities is 22 person-hours. This aligns with the correct answer.

Get further explanation with Examzify DeepDiveBeta

24 person-hours

26 person-hours

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy